Tapestry Friday Update: Week 8

Tapestry Friday Update: Week 8

Hello, Friends of CLDI! Well, the good news is that we beat the cold front that is moving in by getting our footings poured. Pending the weather next week, we will be able to form up and pour the remaining foundational walls. As you can see from the pictures, 3/4 of...

Tapestry Friday Update: Week 5

Tapestry Friday Update: Week 5

Over the holidays and the first part of the New Year, 108 geo piers were set! This process involves drilling large holes in the ground, filling them with aggregate, and then compacting them. This is a technique that more or less creates dense columns of compacted...

Mosaic Senior Cottage Update – Week 32

Hello friends! We are SO CLOSE to having this project fully buttoned up! Thank you First Interstate Bank for your great crew of volunteers to help with a deep clean! As of right now, we are planning on our tenants moving in on April 13th and anticipate by that time...

MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 10

What a great week! I could not be more encouraged and impressed with the progress Langlas construction makes every day. We are thankful that the weather has allowed us to nearly dry the apartments in. Hopefully, in the next week or two, the windows will arrive...

MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 9

We are incredibly thankful for the nice weather we had this week as it afforded us the opportunity to catch up on lost ground caused by the snow last week. With the slabs (concrete floors) poured Thursday, the construction team started framing Friday and on...

MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 7

Wow! What a difference a week can make. Concrete gets poured in the South building this week. Next week they will start to frame the South building. Gravel will also be going into the North building, and then we will be pouring concrete and prepping the...

Mosaic Senior Housing – Friday Update Week 2

We had a great week on-site for Mosaic! Please continue to pray for safety for the workers and favorable weather to forge ahead. Work Completed Stripped topsoilPrepped building slabsTied in to existing sewerTied in to existing waterBegun excavating building footings...