Mosaic Senior Housing – Friday Update Week 2

Sep 3, 2021

Share this post

We had a great week on-site for Mosaic! Please continue to pray for safety for the workers and favorable weather to forge ahead.

Work Completed

  • Stripped topsoil
  • Prepped building slabs
  • Tied in to existing sewer
  • Tied in to existing water
  • Begun excavating building footings for south building

Work Upcoming

  • Finish excavation for south building footings
  • Excavate north building footings
  • Form and tie rebar for south building footings

Share this post

Subscribe for Updates

  • This field is for validation purposes and should be left unchanged.

Related Posts

From a Suitcase to a Home: Lori Finds a New Chapter in Recovery

From a Suitcase to a Home: Lori Finds a New Chapter in Recovery

At 61, Lori wondered if she had waited too long to change her life. Three years sober, she now knows the answer. When Lori entered treatment at age 61, she brought with her a car, a phone, and a suitcase. That was all she had left. Living in Bozeman at the time, Lori...

From Federal Prison to Finding Home: Ron’s Journey to Transformation

From Federal Prison to Finding Home: Ron’s Journey to Transformation

How CLDI's affordable housing became the foundation for one man's remarkable recovery Addiction Fueled By Loss Ron's story begins in Lodge Grass, Montana, where childhood should have been filled with promise. Instead, it was marked by an early introduction to alcohol...

Volunteer

Volunteers are a huge part of our impact on the South Side. We need volunteers to reach and love our neighbors. We would love your help making a difference on the South Side. Reach out, lean into your strengths and together we can increase our impact.  

 

Donate

Without your financial partnership, our efforts would be limited. We are so thankful and honored that you would consider giving. Donations help us dream big, and complete the work He has set out for us on the South Side. One time, monthly, or in other forms, every contribution counts.