We had a great week on-site for Mosaic! Please continue to pray for safety for the workers and favorable weather to forge ahead.

Work Completed

  • Stripped topsoil
  • Prepped building slabs
  • Tied in to existing sewer
  • Tied in to existing water
  • Begun excavating building footings for south building

Work Upcoming

  • Finish excavation for south building footings
  • Excavate north building footings
  • Form and tie rebar for south building footings

Share this post

Follow Us On Facebook

Facebook Pagelike Widget

Subscribe for Updates

  • This field is for validation purposes and should be left unchanged.

Related Posts

Mosaic Senior Housing – Week 3

We have an address! 116 and 114 S 29th Street.Ready for the footings to be poured.The footings are in.Knocking out the essential site development work.Firm foundations.Patched and ready to open!Intern house renovation resumes.Soon to add a garage, two bedrooms, and a...

Mosaic Senior Housing – Groundbreaking!

It has begun! We broke ground for Mosaic Senior Living this week. We are thankful for your faithful support and the Lord's abundant provision. Groundbreaking CeremonyThe SistersGetting ReadyA Good SignBreaking the NewsWhere oh Where is the Sewer Line

Volunteer

Volunteers are a huge part of our impact on the South Side. We need volunteers to reach and love our neighbors. We would love your help making a difference on the South Side. Reach out, lean into your strengths and together we can increase our impact.  

 

Donate

Without your financial partnership, our efforts would be limited. We are so thankful and honored that you would consider giving. Donations help us dream big, and complete the work He has set out for us on the South Side. One time, monthly, or in other forms, every contribution counts.