Tapestry Friday Update: Week 41

Sep 15, 2023

Share this post

Dear CLDI friends and family,

I hope the end of your summer is going well and finds you with the same excitement and anticipation that we have here at the Tapestry construction site. It’s time for another update on our progress, and while the visual transformation may not be as dramatic as before, I want to assure you that we are steadily moving toward the finish line.

In this phase, it’s all about the finer details. We’re currently busy with sheetrock tape and texture, priming, and painting, ensuring that every corner of our project receives the attention it deserves. While it may not be as instantly eye-catching as walls going up or roofs being constructed, these meticulous steps are what truly bring a space to life. The texture of a freshly painted wall, the smoothness of a perfectly taped seam – these are the things that make a house feel like a home. We’re also thrilled to share that our final bathtubs have arrived, and our dedicated team is working diligently to install them. Additionally, we anticipate that the siding work will be substantially completed by the end of next week. Your support has brought us this far, and every brushstroke, every tile laid, is a testament to your generosity and belief in our mission. Thank you for being a crucial part of this journey.

Have a great weekend!

Kaleb Perdew


Share this post

Follow Us On Facebook

Facebook Pagelike Widget

Subscribe for Updates

  • This field is for validation purposes and should be left unchanged.

Related Posts

Tapestry Friday Update: Week 64

Tapestry Friday Update: Week 64

  Hello, Tapestry friends & family! We're excited to announce that with our certificate of occupancy, we are now actively seeking to lease up the apartments at Tapestry. This marks an exciting new phase in our journey as we look for the right individuals and...

Tapestry Friday Update: Week 62

Tapestry Friday Update: Week 62

Our Tapestry Ribbon Cutting was a success! Thank you to all who came out and celebrated with us. Click on the video above to watch entire ribbon-cutting ceremony. There were also two articles written! If you are interested in reading or watching those, the links will...

Tapestry Ribbon Cutting

Tapestry Ribbon Cutting

Tapestry Ribbon Cutting Celebration  CLDI celebrated the near completion of the Tapestry Apartment project with a ribbon-cutting event despite the challenging weather. A great turnout indicates strong community support and engagement. It's important to acknowledge and...

Volunteer

Volunteers are a huge part of our impact on the South Side. We need volunteers to reach and love our neighbors. We would love your help making a difference on the South Side. Reach out, lean into your strengths and together we can increase our impact.  

 

Donate

Without your financial partnership, our efforts would be limited. We are so thankful and honored that you would consider giving. Donations help us dream big, and complete the work He has set out for us on the South Side. One time, monthly, or in other forms, every contribution counts.