Mosaic Senior Housing Update – Week 13

What a great week. We are thankful (and amazed) by this crazy warm fall that has allowed us to get so much construction done without having to deal with the elements. If at some point you would like to go on a tour of our work in the South Side, and such projects as...

Mosaic Senior Housing Update – Week 11

What a great week! It is so fun to drive by each day and see the progress being made. If you haven’t been by in person yet, you should! This week we finished pouring concrete and excavating for carports. The interior and exterior framing was completed,...

MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 9

We are incredibly thankful for the nice weather we had this week as it afforded us the opportunity to catch up on lost ground caused by the snow last week. With the slabs (concrete floors) poured Thursday, the construction team started framing Friday and on...
Mosaic Senior Housing – Friday Update Week 8

Mosaic Senior Housing – Friday Update Week 8

While we thought we were going to poor our first slab last Friday, unfortunately, it didn’t work out. And then with the cold snap, we were delayed. However, the great news is that we poured both slabs Thursday. Next on the docket? Framing both buildings! Cold...