Tapestry Friday Update: Week 40

Tapestry Friday Update: Week 40

Hello, CLDI friends and family, Things continue to move at a steady pace at Tapestry. On our 3rd floor, we are finishing taping and will begin priming and painting next week. The 2nd floor is continuing to drywall. The 1st floor has inspection and then pre-rock...

Tapestry Friday Update: Week 39

Tapestry Friday Update: Week 39

Hello, CLDI friends & family, Progress continues at Tapestry, with the feeder wire being installed this week. The feeder wire is the main power that goes into each of our 27 units. From the outside, our steel siding continues to be installed and will be ongoing...

Tapestry Friday Update: Week 37

Tapestry Friday Update: Week 37

Hello, CLDI friends and family, We have moved down to the 2nd-floor to continue insulating and sheet rocking and to the 1st-floor to finish the electrical. The outside metal siding has officially started; beginning this week and continuing into next week, we will work...

Tapestry Friday Update: Week 36

Tapestry Friday Update: Week 36

Hello CLDI friends, The outside of Tapestry is coming together, with the CMU (Concrete Masonry Units) surrounding the bottom half of the building being completed alongside a beautiful CMU entryway into the building. Next week the black and gray steel siding will go up...

Tapestry Friday Update: Week 30

Tapestry Friday Update: Week 30

Hello Friends of CLDI, This officially makes 30 weeks since we began building Tapestry! It's been incredible to see the hard work and dedication of those invested in seeing Tapestry completed. This week we are finishing up the 3rd-floor interior electrical. All the...

Tapestry Friday Update: Week 23

Tapestry Friday Update: Week 23

Hello friends! I hope this spring weather is finding you well. We are thankful for the spring showers, green grass, tulips, and budding trees! It is a reminder of the HOPE we have in Him. Despite the hard realities that surround us (in our city and world), we have...

Tapestry Friday Update: Week 22

Tapestry Friday Update: Week 22

Happy Spring CLDI friends! Here is a quick update, the 3rd floor is up! We are so pleased with the quick and steady progress being made. It's been fun to look out CLDI's window each week and watch Tapestry being built from the ground up. With your help, you are making...

Dignity & Opportunities Through Rail//Line Coffee

Dignity & Opportunities Through Rail//Line Coffee

Part #2 of Promise’s Story of Healing. Read Part #1 “Healing Her Broken Belief” here.   When Promise first moved into the Hannah House, it felt like she had nothing to offer.She had little job experience and very few skills, but the staff encouraged and supported...

Tapestry Friday Update: Week 10

Tapestry Friday Update: Week 10

Hello Friends of CLDI, Happy Friday! This week we completed the backfill around the foundation and installed the storm drains for the rain leaders on the south side of the building. Due to the cold weather, the ground was frozen, and we had to bring in these special...