The arrival of cold weather and the first flakes of snow remind us of the changing seasons. As winter has officially wrapped around us here at Tapestry, let us share our update!
Up on the third floor, things are really coming together. The bathrooms are all caught up, and we’re busy staging and installing cabinets; we’ve even begun adding flooring! It is exciting to begin adding those essential finishing touches.
The 2nd floor is still being painted, and for the first floor, we’ve made significant progress. The soffits are being hung, and we’re in the final stages of framing the last few. On the outside, site work for concrete is ongoing, giving the surroundings a fresh, new look. And our work on the electrical transformer pad is progressing steadily.