Hello, CLDI friends and family,
Things continue to move at a steady pace at Tapestry. On our 3rd floor, we are finishing taping and will begin priming and painting next week. The 2nd floor is continuing to drywall. The 1st floor has inspection and then pre-rock beginning next week. Some things to look forward to are the siding being completed in another week and our work beginning on sidewalks and filling in asphalt in two weeks.
We hope you are able to enjoy the last few weeks of summer despite the heavy smoke we have been getting.
Blessings,
Kaleb