Hello CLDI friends,
The outside of Tapestry is coming together, with the CMU (Concrete Masonry Units) surrounding the bottom half of the building being completed alongside a beautiful CMU entryway into the building. Next week the black and gray steel siding will go up on the south side of the building, along with gutters and downspouts. Sheet rockers are moving from the 3rd floor, going down with the lids done, and prepping for HVAV ductwork. The electricians are already down to the first floor, having completed the 3rd and 2nd floors.
If you would like to take a tour of the building or drive by to see Tapestry’s new look, please reach out at kaleb@cldibillings.org.
Have a great weekend!
Kaleb