Hello Friends of CLDI!
Happy Friday! Some good news, Tapestry’s sewage tie-in to the city will be complete today or tomorrow. Our lumber has also arrived at the warehouse, and next week, they will start framing walls off-site. Unfortunately, with the extreme weather, the frozen ground created too much moisture in the dirt to allow us to begin the underground plumbing work. We are delayed roughly 10 days and are working to dry up the ground. Although we are behind, 1) we expected that we might hit some rough weather; we do live in MT, after all, and 2) we plan to make up some ground once we begin framing.
We would love to give you a tour of the building site as well as the other works of CLDI. Click here to set up a time to meet!
Blessings,
Kaleb