I hope you had a Merry Christmas and a Happy New Year filled with joy! As we step into the new year, let’s dive into the latest happenings at Tapestry.

The cleanup on the third floor has begun, and it’s nothing short of incredible! With the exception of water heaters and refrigerators, the spaces are looking move-in ready. The transformation is truly remarkable.

Moving down to the second floor, the addition of door jambs and trim is underway, and the electrical work is about 90% complete. Each detail is carefully attended to, bringing us closer to the envisioned completion.

On the first floor, progress is evident as we begin adding cabinets and countertops, along with doors and their jambs. The groundwork for functional and aesthetically pleasing spaces is taking shape.

Good news on the elevator front – it’s fully operational using a generator. We’re hopeful that Northwestern Energy will be on-site next week to set up permanent power, allowing us to add the remaining appliances and bring Tapestry one step closer to its completion.

As we navigate these final stages, please continue to keep the dedicated team at Langlas in your thoughts and prayers. Their hard work and commitment are instrumental in ensuring we meet our project deadlines.

Thank you for your continued support and prayers. Here’s to a year filled with progress, growth, and the realization of the Tapestry vision.

Blessings,

Kaleb Perdew


Share this post

Follow Us On Facebook

Facebook Pagelike Widget

Subscribe for Updates

  • This field is for validation purposes and should be left unchanged.

Related Posts

Tapestry Friday Update: Week 64

Tapestry Friday Update: Week 64

  Hello, Tapestry friends & family! We're excited to announce that with our certificate of occupancy, we are now actively seeking to lease up the apartments at Tapestry. This marks an exciting new phase in our journey as we look for the right individuals and...

Tapestry Friday Update: Week 62

Tapestry Friday Update: Week 62

Our Tapestry Ribbon Cutting was a success! Thank you to all who came out and celebrated with us. Click on the video above to watch entire ribbon-cutting ceremony. There were also two articles written! If you are interested in reading or watching those, the links will...

Tapestry Ribbon Cutting

Tapestry Ribbon Cutting

Tapestry Ribbon Cutting Celebration  CLDI celebrated the near completion of the Tapestry Apartment project with a ribbon-cutting event despite the challenging weather. A great turnout indicates strong community support and engagement. It's important to acknowledge and...

Volunteer

Volunteers are a huge part of our impact on the South Side. We need volunteers to reach and love our neighbors. We would love your help making a difference on the South Side. Reach out, lean into your strengths and together we can increase our impact.  

 

Donate

Without your financial partnership, our efforts would be limited. We are so thankful and honored that you would consider giving. Donations help us dream big, and complete the work He has set out for us on the South Side. One time, monthly, or in other forms, every contribution counts.