MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 9

We are incredibly thankful for the nice weather we had this week as it afforded us the opportunity to catch up on lost ground caused by the snow last week. With the slabs (concrete floors) poured Thursday, the construction team started framing Friday and on...
Mosaic Senior Housing – Friday Update Week 8

Mosaic Senior Housing – Friday Update Week 8

While we thought we were going to poor our first slab last Friday, unfortunately, it didn’t work out. And then with the cold snap, we were delayed. However, the great news is that we poured both slabs Thursday. Next on the docket? Framing both buildings! Cold...

MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 7

Wow! What a difference a week can make. Concrete gets poured in the South building this week. Next week they will start to frame the South building. Gravel will also be going into the North building, and then we will be pouring concrete and prepping the...

MOSAIC SENIOR HOUSING – FRIDAY UPDATE WEEK 6

Foundation walls; check.Site prepThe challenges next door; hopeful the city will enforce a demolition.The worksiteGetting the walls formed for Building #2Building #1 plumbed and ready for the concrete slab pour!Future intern house at 2016 4th Avenue SouthOur neighbors...

Mosaic Senior Housing – Friday Update Week 5

Construction forges ahead. The warm fall has been favorable for building! Have you seen the architect renderings for Mosaic? Enjoy these pictures of what’s to come.  Do you have a favorite feature? We love the front porches and proximity to Rail//Line....